A wide hinterland

Kaohsiung Intercontinental Port Phase 1 A6-B Land


Significant Milestone :

  • Signed a contract with TIPC in March 2022.
  • Obtained a construction permit from TIPC in 2023.
  • Estimated Jacket production line completion is 2024 Q4



Land Planning :

  • The size of the land area is 17,2 hectares.
  • Workshop for manufacturing components. 200m x 50m.
  • Capacity of storage medium and large components.
  • The land is planned to be used to build a Research and Manufacturing Centre for marine and Green energy, jackets foundations, wind float, foundations assembly, storage area and load out.

Significant Milestone :

  • Signed a contract with TIPC in March 2022.
  • Obtained a construction permit from TIPC in 2023.
  • Estimated Jacket production line completion is 2024 Q4


Land Planning :

  • The size of the land area is 17,2 hectares.
  • Workshop for manufacturing components. 200m x 50m.
  • Capacity of storage medium and large components.
  • The land is planned to be used to build a Research and Manufacturing Centre for marine and Green energy, jackets foundations, wind float, foundations assembly, storage area and load out.

Equipped with state-of-the-art facilities factory

400-Meter Factory


Factory Space :

  • Length of 400m
  • Width of 50m
  • Height of 50m
  • Incoming steel plates receiving / inspections / cutting / beveling / milling / rolling / fit-up / welding

 

Land Planning :

  • Fabrication activities will be implemented in line with fabrication sequence, including tubular manufacturing, pre-fabrication, assembly, erection, testing. Components for offshore structures such as legs, nodes, cones, pin piles.
  • Fabrication with continuous production methods and smart auto facilities.
  • The factory is planned to launch its fabrication in the third quarter of 2023.

Factory Space :

  • Length of 400m
  • Width of 50m
  • Height of 50m
  • Incoming steel plates receiving / inspections / cutting / beveling / milling / rolling / fit-up / welding

 

Land Planning :

  • Fabrication activities will be implemented in line with fabrication sequence, including tubular manufacturing, pre-fabrication, assembly, erection, testing. Components for offshore structures such as legs, nodes, cones, pin piles.
  • Fabrication with continuous production methods and smart auto facilities.
  • The factory is planned to launch its fabrication in the third quarter of 2023.