A wide hinterland
Kaohsiung Intercontinental Port Phase 1 A6-B Land
Significant Milestone :
- Signed a contract with TIPC in March 2022.
- Obtained a construction permit from TIPC in 2023.
- Estimated Jacket production line completion is 2024 Q4
Land Planning :
- The size of the land area is 17,2 hectares.
- Workshop for manufacturing components. 200m x 50m.
- Capacity of storage medium and large components.
- The land is planned to be used to build a Research and Manufacturing Centre for marine and Green energy, jackets foundations, wind float, foundations assembly, storage area and load out.
Significant Milestone :
- Signed a contract with TIPC in March 2022.
- Obtained a construction permit from TIPC in 2023.
- Estimated Jacket production line completion is 2024 Q4
Land Planning :
- The size of the land area is 17,2 hectares.
- Workshop for manufacturing components. 200m x 50m.
- Capacity of storage medium and large components.
- The land is planned to be used to build a Research and Manufacturing Centre for marine and Green energy, jackets foundations, wind float, foundations assembly, storage area and load out.

Equipped with state-of-the-art facilities factory
400-Meter Factory
Factory Space :
- Length of 400m
- Width of 50m
- Height of 50m
- Incoming steel plates receiving / inspections / cutting / beveling / milling / rolling / fit-up / welding
Land Planning :
- Fabrication activities will be implemented in line with fabrication sequence, including tubular manufacturing, pre-fabrication, assembly, erection, testing. Components for offshore structures such as legs, nodes, cones, pin piles.
- Fabrication with continuous production methods and smart auto facilities.
- The factory is planned to launch its fabrication in the third quarter of 2023.
Factory Space :
- Length of 400m
- Width of 50m
- Height of 50m
- Incoming steel plates receiving / inspections / cutting / beveling / milling / rolling / fit-up / welding
Land Planning :
- Fabrication activities will be implemented in line with fabrication sequence, including tubular manufacturing, pre-fabrication, assembly, erection, testing. Components for offshore structures such as legs, nodes, cones, pin piles.
- Fabrication with continuous production methods and smart auto facilities.
- The factory is planned to launch its fabrication in the third quarter of 2023.